Rigid Inclusions, Alexandra Dock, Liverpool | CFA Piling | Keller UK

Rigid Inclusions, Alexandra Dock, Liverpool

 

At the site of a former warehouse within Alexandra Dock, Liverpool, Keller have installed their patented system to support a new distribution facility. The system, which has previously been used by Keller in France and Germany, utilizes a stiff column within weak soils which is overlain by a Load Transfer Platform  which in turn supports a ground bearing slab.

At Liverpool, the columns consist of 340mm diameter Driven Cast In Situ piles driven down into the dense sands. Close to a culvert, these piles were substituted by two rows of 450mm dia Continuous Flight Auger Piles.

As with any distribution warehouse, supporting the floor to the specified tolerance is the most important aspect of the project. Working closely with McLaughlin & Harvey  to develop the best solution, finite element analysis was undertaken to model settlements at various spacings of columns and thicknesses of mattress. At Alexandra Dock the floor columns are at centres of  2.5m and overlaying these is a 500mm thick mattress consisting of heavily rolled 6F2 stone. Some 4412 columns support the building.

The very dense sub base sitting beneath the old slab actually was suitable as a piling mat following rigorous load testing carried out by McLaughlin & Harvey. Once the stiff column is installed the upper part of it is removed down to the base of the granular mattress and replaced with dense gravel. The mattress is then topped up in thickness.

This system fits neatly between vibro techniques and piling. Provided site levels allow the construction of a load transfer mattress it can be adopted where the soils are too soft or too organic for vibro. Clearly in certain parts of the country the granular mattress may be too expensive or indeed not available and a two-way suspended slab will be the optimum solution. At Alexandra Dock the existing granular material was incorporated into the load transfer mattress adding to the savings.

 

Client: Peel Ports

Main Contractor: McLaughlin & Harvey

Floor Design Load: 75kN/m2